Queensland has a very long  high voltage transmission grid that extends 1,700km from north of Cairns to the New South Wales border. Apart from the populated south east corner and the industrialised Gladstone region this long grid feeds a state with a low population density.
The Queensland’s electricity transmission network currently comprises 275kV transmission lines from Cairns to the southern Gold Coast, with 110kV and 132kV transmission lines providing transmission in local areas and supporting the 275kV network.
In addition, 330kV transmission lines link Queensland to the New South Wales network, allowing the flow of high voltage electricity between the two States.
A 500kV transmission network is being introduced in South East Queensland. Note that one 500kV power line is capable of carrying about the same amount of electricity as three 275kV transmission lines, with a much smaller land use requirement.
Queensland is Australia’s most energy hungry state on a per capita basis. Currently 72.2% of electricity generated in that state comes from fossil fuels. Even with proposed renewable energy projects the actual CO2 emissions intensity will only reduce marginally because of the poor capacity factors of wind and solar generation and the backup required from gas plants in particular.
The generating units at coal fired plants such as Stanwell, Gladstone, Tarong and Callide are not especially large being in the range of 350MW to 450MW and are matched to a 275kV transmission system.
The performance of the Queensland generating system as a whole is shown in the following table for 2024.
| Generator | Capacity (MW) | Proportion | Output (GWh) | Proportion | Capacity Factor |
| Coal | 8,130 | 64.1% | 42,867 | 65.0% | 0.61 |
| CCGT | 1,418 | 5.0% | 3,316 | 5.0% | 0.27 |
| OCGT | 1,603 | 1.4% | 919 | 1.4% | 0.07 |
| Gas CM | 2,256 | 0.7% | 438 | 0.7% | 0.02 |
| Wind | 1,018 | 4.5% | 2,933 | 4.4% | 0.33 |
| Solar Utility | 4,640 | 9.1% | 6,069 | 9.2% | 0.15 |
| Solar R/T | 6,082 | 12.7% | 8,523 | 12.9% | 0.16 |
| Hydro | 164 | 2.2% | 457 | 0.7% | 0.32 |
| Recip Eng | 189 | 0.1% | 40 | 0.1% | 0.02 |
| Hydro PS | 540 | 0.0% | |||
| Biomass | 30 | 0.3% | 217 | 0.3% | 0.83 |
| Battery | 507 | 0.2% | 144 | 0.2% | 0.03 |
| 26,577 | 100.3% | 65,923 |
Total electricity generating capacity (not including storage) in Queensland in 2024 was 25,530MW which generated 65TWh of gross electricity production[ii].
Queensland provides about 31% of the nuclear plant capacity requiring:
Smaller 1.05GW plants could also be used. Based on our discussions with South Korean nuclear power plant constructors, plants need to be built in multiples at each site to achieve their greatest economies. Cooling capacity will therefore be required to suit at least 2.8GW for large plants at these locations. In Queensland, the largest cooling capacity can be obtained from seawater cooling on both coastal and estuarine sites.
Cooling at inland locations is unlikely to be available for large plants though water extraction from the Fitzroy River could possibly be increased to enable the Stanwell site to be used. Other inland sites don’t have sufficient cooling water capacity for large plants. The option to use multiples of smaller 300MW units exists though they come at a significant cost premium.
In Table 3 we have listed nine locations based primarily on ensuring sufficient cooling capacity is available. For this reason we have concentrated on coastal locations and major estuaries. Many other sites are available on Queensland’s vast coast line. We have also attempted where possible to minimise grid upgrades.
Table 3 – Various sites reviewed for Queensland Nuclear Power Plants
| Cooling Resource | Cooling Type | |
| Thompsons Point | Fitzroy River | Estuary |
| Stanwell | Fitzroy River | Freshwater |
| Curtis Island | Keppel Bay | Seawater |
| Boyne River/Tannum Sands | Boyne River | Estuary |
| Hummock Hill Island | Rodd Bay | Seawater |
| Rodd Bay | Rodd Bay | Seawater |
| Miara | Coral Sea | Seawater |
| Tandora | Mary River | Estuary |
| Tinnanbar | Great Sandy Strait | Estuary |
Nuclear power plants can be constructed at most of these sites however on a quite subjective basis we have selected three sites for deployment. These are listed in Table 4 – Possible mix to meet planned energy needs.
Table 4 – Possible mix of sites to meet planned energy needs
| Location | 2050 | 2060 | |||
| Capacity MW | Number of Units | Capacity MW | Number of Units | Cooling Type | |
| Thompson Point | 2.8 | 2 | 2.8 | 2 | Estuary |
| Rodd Bay | 2.8 | 2 | 2.8 | 2 | Seawater |
| Tandora | 0 | 0 | 2.8 | 2 | Estuary |
| Total | 5.6 | 4 | 8.4 | 7 | |


| Site | Location | Number of SNPP’s | Cooling |
| Probables | |||
| MN – 3 | Millmeran | 2 x 300MW | Evaporative and Hybrid |
| CA – 6 | Callide | 4 x 300MW | Evaporative and Hybrid |
| GD – 6 | Gladstone | 6 x 300MW | Ist pass from sea |
| RR – 2 | Ross River | 2 x 300MW | Evaporative and Hybrid |
| TR – 6 | Tarong | 4x 300MW | Evaporative and Hybrid |
| ST – 5 | Stanwell | 4 x 300MW | Evaporative and Hybrid |
| WH – 2 | Wivenhoe Dam | 2 x 300MW | Evaporative and Hybrid |
| Total | 24 x 300MW | ||
| Â | Â | ||
| Possibles | |||
| SV – 2 | Samsonvale | 2 x 300MW | Evaporative and Hybrid |
| BN – 2 | Burdekin | 2 x 300MW | Evaporative and Hybrid |
| SH – 2 | Stockleigh | 2 x 300MW | Evaporative and Hybrid |
| Total | 6 x 300MW |
In Queensland coal fired plants were constructed adjacent to available coal mines and other infrastructure.
New nuclear plants will where possible take advantage of the resource used for cooling at these plants.
At Townsville and Gladstone sea water cooling will be used
In an effort to reduce the environmental impact upon inland water resources, modern nuclear power plants are being designed to use a hybrid system of air and water cooling. During periods of low water availability the degree of air cooling can be increased though at a modest reduction in power output.
The tabulation shows the anticipated type of cooling at each plant
Australia’s long coastlines provide many options for locating nuclear power plants
To overcome issues surrounding temperature rises in inland locations cooling towers or mechanically driven systems known as hybrid and recirculating systems can be used. These are now the only option used in the United States under their EPA guidelines.
While recirculating systems don’t add heat to the river or lake, they do consume water through evaporation. In Australia the availability of sizeable inland rivers are limited though a number of large reservoirs such as Wivenhoe Dam provide a substantial resource for fresh water cooling.
An excellent and detailed outline of the cooling options is available at:Â Cooling Power Plants | Power Plant Water Use for Cooling – World Nuclear Association